MS Project 2013 Examination: Time 45 minutes

MSME MS Project 2013
Max Marks: 45 (Pass Percentage 70%) Instructions This question paper consists of multiple choice questions. Each question carries 1 point. There is no negative marking Each question has only ONE correct response. In case more than one response seems feasible, pick the best possible response Candidates are required to mark their questions on the questions paper itself This is an open book exam and you can use the printed material provided by MSME or any other MS Project book Please write your name on the question paper, the exact format that you would like your name to appear in the MSME MS Project 2013 Completion Certificate

1 2 3 4 5

I affirm that I am providing accurate self identification below. I pledge that I will not attempt to copy in the exam or disclose the answers to any of the other participants in the exam

Name:__________________________

Signature___________________________

MS Project 2013 Examination: Time 45 minutes

1. PDM refers to
a) Post Diagramming Method b) Pre Descriptive Method c) Precedence Diagramming Method d) Program Diagramming Method

2. Dummy activities in a network refers to
a) b) c) d) Frequently occurring activity Activity of zero duration Unwanted activity Tiresome activity

3. The file extension in MS Project is
a) b) c) d) .mppx .mpsx .mptx .mpax

4. The default fiscal year in MSP starts in
a) b) c) d) January April June November

5. AOA network refers to
a) b) c) d) PERT GERT PDM CPM

6. The primary elements of Project Management are
a) b) c) d) Planning & Scheduling Control & Monitoring Scheduling & Control Planning & Controlling

MS Project 2013 Examination: Time 45 minutes

7. Critical Path Method is used to construct network based on
a) b) c) d) Events Activities Both None

8. PERT is acronym for
a) b) c) d) Program Evaluation & Review Technique Project Evaluation & Resource Technique Project Evaluation & Review...

Show More


Citations

MLA Citation

"Msp-2013 Basic Concept of the Software...". Anti Essays. 10 Dec. 2018

<http://parimatchstavki7.com/free-essays/Msp-2013-Basic-Concept-Of-The-Software-588236.html>

APA Citation

Msp-2013 Basic Concept of the Software.... Anti Essays. Retrieved December 10, 2018, from the World Wide Web: http://parimatchstavki7.com/free-essays/Msp-2013-Basic-Concept-Of-The-Software-588236.html